• Construction of (1) Gasoline storage tank (2.5 Mm3) at MISR and the construction of (1) spherical tank (4 Mm3) at Alexandria at Petrogas. The estimated cost is LE 26.5 MM.   .


• Replacement and renewal of (8) petroleum products storage tanks with total capacity of about 31.5 Mton at COOP/ APRC/ SOPC. The estimated cost is LE 27 MM.


• Construction of (4) petroleum products pipelines at SOPC/PPC with total estimated cost LE196 MM:
o Dekhela/ Wadi AlQamar new LPG PL 12"/7 km
o Abu Rudis/ Wadi Feran tanks new LPG PL 12"/13 km
o Banha/ Tanta Products section 16"/53 km From Mostorod/Tanta PL
o SOPC/ Suez new steam power station fuel oil feeding PL 12"/684 m
 


• Construction of a new furnace for the atmospheric unit F-1/ rehabilitation of (10H-2) furnace at SOPCO coke complex with expected cost of about LE 57 MM.


• Supply of (69) tractor heads and half trailer at MISR/ COOP. The estimated cost is LE 75 MM.    


• Establishment a new platform for petroleum products at ElMax storage and modernization of the Hurgada airport Aircraft Supply Service Station and the tie in to the Hyderant network. In addition, Portsaid airport Aircraft Supply Station and the construction of (11) storage tanks for aircraft supply units at MISR. The total estimated cost is LE 32 MM.    


• Developing (97) car service and fuel stations at MISR/ COOP with total estimated cost LE 26 MM.    


• Infrastructure preservation for different petroleum companies (thermal treatment for LPG cylinders' maintenance / Upgrade The mixing unit of petroleum oils/ electric transformers and panels/ upgrade IT system/ compressors/ air coolers/ steam boilers). The estimated cost is LE 129 MM.    


• Fire water network/ alarm systems and firefighting networks/ offshore platforms rehabilitation/ units thermal lining/ pipe racks at (NPC- SOPCO- APRC- Petrogas- GPC- COOP- MISR- CORC) for safety insurance against fire, gas leakage and environmental contamination. The estimated cost is LE 69 MM.